Complete Installation Process
| Step | What Happens | Time |
|---|---|---|
| 1. Free Site Survey | Engineer visits, checks roof, shading, load analysis | Day 1 |
| 2. Quotation | Detailed proposal with system specs & pricing | Day 1-2 |
| 3. DISCOM Application | NOC/approval application to MPPKVVCL | Day 3-10 |
| 4. Material Delivery | Panels, inverter, structure delivered to site | Day 10-12 |
| 5. Installation | Structure, panels, wiring, inverter installation | Day 12-14 |
| 6. Net Meter Application | Applied to DISCOM for bidirectional meter | Day 14 |
| 7. DISCOM Inspection | Engineer inspects the installation | Day 20-35 |
| 8. Commissioning | Net meter installed, system goes live! | Day 35-45 |
What You Need to Provide
- Clear roof access for survey and installation
- Electricity connection details (consumer number)
- Documents for DISCOM application
- Advance payment as per agreement
💡 Tip: System starts generating electricity from Day 14 itself. The net meter just formalizes the export billing.