Solar Panel Installation Process in Ratlam — From Survey to Switch-On

By Kalash Energy, Ratlam · · 5 min read · हिंदी में पढ़ें

What happens from day 1 to the day your solar system starts generating electricity. Full timeline explained.

Complete Installation Process

StepWhat HappensTime
1. Free Site SurveyEngineer visits, checks roof, shading, load analysisDay 1
2. QuotationDetailed proposal with system specs & pricingDay 1-2
3. DISCOM ApplicationNOC/approval application to MPPKVVCLDay 3-10
4. Material DeliveryPanels, inverter, structure delivered to siteDay 10-12
5. InstallationStructure, panels, wiring, inverter installationDay 12-14
6. Net Meter ApplicationApplied to DISCOM for bidirectional meterDay 14
7. DISCOM InspectionEngineer inspects the installationDay 20-35
8. CommissioningNet meter installed, system goes live!Day 35-45

What You Need to Provide

💡 Tip: System starts generating electricity from Day 14 itself. The net meter just formalizes the export billing.